Case Studies

Results From the Field

A selection of facility design and layout planning engagements across the Southeast United States. All metrics reflect post-implementation performance measured at 12 months.

Featured Project
Automotive Assembly

Greenfield Assembly Plant — Central Alabama

A Tier 1 automotive supplier needed a 480,000 sq ft assembly facility designed from the ground up to support a new OEM contract with a 14-month delivery window. Koolrula led full facility design, production zone layout, and implementation management from site selection through commissioning.

Greenfield DesignAutomotiveImplementation Management
480Ksq ft
Facility footprint designed
14months
Design-to-commissioning timeline
23%
Reduction in material handling distance
$4.2M
Estimated annual logistics savings
Distribution & Logistics
GA

Regional Distribution Center Reconfiguration

Savannah, Georgia

Challenge

A national retailer's Southeast distribution hub was operating at 94% capacity with no room to expand vertically. Throughput had plateaued and labor costs were rising due to inefficient pick paths.

Approach

Koolrula conducted a full current-state operational audit, mapped all material flows, and modeled 4 alternative layout configurations. The selected design introduced a zone-based slotting strategy and reconfigured inbound staging to free 18% of floor space.

31%
Increase in daily throughput
18%
Floor space recovered
$1.8M
Annual labor cost reduction
6 mo
Implementation timeline
Layout OptimizationDistributionLean
Food & Beverage Processing
TN

Processing Plant Capacity Expansion

Memphis, Tennessee

Challenge

A regional food manufacturer needed to increase production capacity by 40% without expanding their existing 220,000 sq ft footprint. Existing layout had grown organically over 15 years and contained significant flow inefficiencies.

Approach

We performed a detailed bottleneck analysis across all production lines, identified three critical constraint points, and redesigned the production zone layout to eliminate cross-traffic and reduce changeover distances. Phased implementation kept the facility at 80%+ production throughout.

44%
Capacity increase achieved
0 sq ft
New construction required
19%
Reduction in changeover time
8 mo
Phased implementation
Capacity PlanningFood ProcessingBrownfield
Heavy Manufacturing
SC

Heavy Fabrication Shop Redesign

Spartanburg, South Carolina

Challenge

A structural steel fabricator was experiencing chronic bottlenecks at their welding stations and excessive crane travel distances that were limiting throughput and creating safety risks on the floor.

Approach

Koolrula mapped crane utilization patterns, material staging sequences, and weld queue data over a 30-day baseline period. The redesigned layout repositioned fabrication cells to minimize crane travel, introduced dedicated staging lanes, and separated pedestrian and material flow paths.

38%
Reduction in crane travel distance
27%
Throughput increase
Zero
Recordable safety incidents post-implementation
$920K
Annual productivity gain
Layout RedesignHeavy ManufacturingSafety
Pharmaceutical
NC

GMP-Compliant Facility Design

Research Triangle, North Carolina

Challenge

A contract pharmaceutical manufacturer needed a new 95,000 sq ft facility designed to meet FDA GMP requirements while maintaining the operational flexibility to serve multiple product lines simultaneously.

Approach

Koolrula led facility design in close coordination with the client's regulatory team, designing cleanroom zones, material airlocks, personnel flow paths, and utility routing to meet 21 CFR Part 211 requirements. 3D modeling enabled early regulatory review and reduced design revision cycles.

95K sq ft
GMP-compliant facility designed
100%
First-pass FDA inspection result
3
Simultaneous product lines supported
11 mo
Design-to-occupancy timeline
GMP DesignPharmaceuticalRegulatory Compliance
Aerospace & Defense
AL

Aerospace Component Assembly Optimization

Huntsville, Alabama

Challenge

A defense contractor's component assembly operation was failing to meet production rate targets due to a layout that had not been updated since the facility opened in 2009. Work-in-process inventory was accumulating between stations and on-time delivery performance had declined to 71%.

Approach

We applied value stream mapping across all assembly sequences, identified seven non-value-adding transport steps, and redesigned the cell layout to create a continuous flow configuration. Workstation ergonomics were also addressed as part of the redesign.

71→96%
On-time delivery improvement
62%
Reduction in WIP inventory
7
Non-value-adding transport steps eliminated
$2.1M
Annual cost avoidance
Value Stream MappingAerospaceContinuous Flow
Chemical Processing
MS

Chemical Plant Safety & Flow Redesign

Pascagoula, Mississippi

Challenge

A specialty chemical processor needed to reconfigure their production floor to meet updated OSHA PSM requirements while also addressing chronic congestion in their raw material receiving and finished goods staging areas.

Approach

Koolrula performed a hazard-aware layout analysis, established required separation distances for all chemical storage zones, and redesigned material flow paths to eliminate congestion points. All layout decisions were reviewed against PSM compliance requirements throughout the design process.

100%
PSM compliance achieved
41%
Reduction in receiving congestion incidents
15%
Improvement in material cycle time
5 mo
Implementation timeline
PSM ComplianceChemical ProcessingSafety

Discuss Your Facility Challenge

Every engagement starts with a conversation. Tell us about your operation and we'll outline what's possible.